MEDIEVAL FLOOR DISCOVERED DURING SITE WORKS: ST MARY'S CHURCH, HUGGATE

We have had an exciting year so far at Shaw and Jagger with many more projects now starting on site as the weather improves.

One of our major projects is the re-ordering of St Mary’s Church in Huggate. This has included removing the old Victorian raised floor and fixed pews with a new insulated limecrete floor being funded by the NHLF with works being completed by Pinnacle Conservation Building Contractors.

During investigations and the removal of the floor, archaeologists have discovered multiple items of interest including an old gravestone dating to the 18th century as well as a hearth and remains of the medieval floor. We even discovered a carving of a ship behind old pipework.

We are now in the process of detailing a glass floor element to enable visitors and parishioners to enjoy this incredible find for many years to come.

SEASONS GREETINGS

This year has been a very busy one here at Shaw and Jagger. We have had Becky and John join the team who have been incredibly helpful in delivering lots of fantastic projects. Becky saw the completion of her degree and passing her driving test! Matt has become a father for the first time and so we have been enjoying lots of photos and even a visit. We had two big birthdays and lots of fun things inbetween.

Work wise, we have had multiple planning and listed building consents throughout the year, a combination of a lot of patience, hard work and engagement. We are looking forward to delivering some really exceptional schemes in 2024 both for the residential and ecclesiastical sector.

But now we wind down for Christmas, with our office closing from Friday 22nd December, reopening on 8th January 2024.

Wishing you all a very Merry Christmas and very happy 2024.

ON SITE: BLACKBURN CATHEDRAL STABILISATION AND RE-POINTING WORKS TO THE LANTERN TOWER

Blackburn Cathedral is a fantastic collective of 19th and 20th-century architecture. It’s central Lantern tower with its slim, and dominant spire is a hallmark of Blackburn The building is of local and national importance.

Louise is their Cathedral Architect and requested a detailed inspection following concerns raised during the Quinquennial inspection regarding the condition of the Lantern Pinnacles. A high level inspection was completed in Spring 2023 by Fogarty Steeple Jacks in association with Heritage Limited

The findings were that there were many open joints and some were beginning to de-stabilise. A long-term strategy will be required to re-build the pinnacles but in the meantime, a series of stabilisation works have been in the process of completion. This has included lifting and re-bedding the most vulnerable pinnacles with additional support. All open joints have been raked out and repointed. Additionally, the stained glass was bed in a cementitious mortar (quite unusual) and where it has been safe to do so, this has been removed and re-sealed with a flexible putty.

Works have been undertaken using specialist the same specialist Steeple Jacks and the work is a significant improvement and will help continue the longevity of this fantastic Cathedral.

PLANNING PERMISSION ACHIEVED FOR A NEW OUTDOOR KITCHEN AND SUMMER HOUSE

On the boundary of the Yorkshire Dales at the mouth of Wensleydale lies a series of small hamlets and villages that overlook Penhill, a beautiful and domineering hill.

We have been working with this client for some time recently completing a double extension and internal alterations and have now been granted planning permission for the next phase. The works include new garaging, an outdoor kitchen and summer house. The new bi-fold doors and opening will provide far-reaching views over to Penhill and the Wensleydale Railway.


We look forward to sharing photos once it has been completed!

PLANNING AND LISTED BUILDING CONSENT ACHIEVED FOR COUNTRY HOUSE

We are delighted to confirm a new planning and listed building consent has been granted for the conservation and alterations to a Grade II listed dwelling, designed by William Butterfield.

The project set in North Yorkshire, is a large dwelling built for the Estate Manager for the local Landowners Estate. The house has seen numerous unfavourable works completed over the years, including the removal of original stone mullioned timber windows for double glazed UPVC along with cementitious damp proof coursing and a lot asbestos although the main building form and out buildings remain largely unchanged.

The consented proposals include the conservation and repair works to the roof including the chimneys, as well as replacing the cementitious renders to the lower levels and localised stone repairs.

Internally the works include a new shower and bathroom, a new kitchen and back kitchen, opening up the living room and dining room and large doors leading to the garden which currently has very poor access. New paving and a new opening to the garden wall will also be completed in the coming months.

Many of the remaining original features will also be retained and restored including original fireplaces, wood panelling, skirtings, flooring and cabinetry in the pantry and larder.

We are looking forward to seeing this beautiful building brought back to life and lovingly restored.

Ferry Cottage Wins Design Award!

We are delighted to announce that our work on Ferry Cottage has just received an award for ‘good contemporary design’ by the York Design Awards.

About Ferry Cottage

Ferry cottage is within sight of the river Ouse and adjacent to a Grade I listed building, the new house adheres to the roof ridge height of its dilapidated predecessor but makes use of a single-storey element to extend the living space into the site. ​​​​​​

​​​​​​​This new family home is constructed using brick and zinc this home has high levels of insulation and makes use of high-quality materials and finishes both inside and out.

The house is highly energy efficient using ground source heat pumps as well as photovoltaic panels to compliment them. A large plant room in the detached garage connects to the house via the gravel vehicle forecourt. The fabric of the house is incredibly well constructed and finished to ensure the optimum performance of the renewable energy sources.

On site: St Andrew’s Church

Louise is church architect to St Andrew’s Church and following the Quinquennial Inspection (A survey required of all churches every 5 years) it was discovered that there were many open joints to the copings and to the tower. Over the next year a plan was put in place to undergo the necessary repairs.

The church is currently undergoing coping and roof repairs to its nave and chancel, as well as the tower being completed re-pointed. The two pre-reformation bells have been identified by bell specialist John Arthur as being cast by Johannes de Copgrave in 1399. Bells cast by him are found at Boynton, Grisby ex (Stockburn), here 2 bells, Luftus (recast 1811), and Scrawton, so 5 bells remain intact. What I find interesting is that the majority of these bells are within a confined area of North Yorkshire with a couple a little wider. He may well not have had a fixed base but may well have been an itinerant founder casting on site.Originally both bells would have had cast in wrought iron staple sfrom which the clappers would have been hung. Mr Clouston reported that the treble bells had had a staple “cemented” into position and I would add that from the holes in the crown of the tenor bell a “false” staple may well have been fitted at some time.

The works are being completed under a JCT Minor Works Contract by Pinnacle Conservation with Shaw and Jagger acting as Contract Administrators.

Lingholm Boathouse, Derwentwater

We had perfect weather for this months site visit to the new boathouse construction site at the Lingholm Estate. 

Upon arrival the concrete reinforcement was all complete atop the piling mat and pile heads, and was waiting for the concrete slab pour in the early afternoon once the sun had moved behind the trees and cast some shade over the site. Despite having a tricky access arrangement the pour went smoothly with the assistance of a 20m truck mounted concrete pump. Six mixers later and the pour was complete and levelled off.

We cant wait to see the building move forward from this point with the base walls being completed in the coming weeks. The steel frame is currently in production and is due to arrive on site in just under a month, and we are currently working with the window and classing suppliers to follow suit. The next few weeks and months will be very exciting for this project.

New Dwelling Harrogate - COMPLETED

The new build 5 bedroom detached house which started on site in August 2017 is now complete and looks great! Externally the new dry stone boundary wall and landscaping create the perfect setting for this house which blends into the local vernacular with the use of stone and its modern elements really enhance it.

Features such as the stone detailing, large windows and balcony to the master bedroom are modern elements based on traditional methods which only a new build house can provide for a client. Internally the ground floor has stone flags throughout suitable for the underfloor heating. Simple bulkhead details in the ceiling help define spaces and add interesting features to the larger rooms. The kitchen dining area features a higher ceiling and larger windows, great for entertaining.

The ground and first floor are linked by a feature staircase with timber treads and glass balustrade. The timber used on the treads is used throughout as a floor covering with complimentary traditional style doors. The bathroom and en-suites are finished with modern low level shower trays and glass screens. A great project to be involved with and one which the client was extremely happy with the end product.

Replacement Dwelling Harrogate - Completed

Started in September 2016 this 3 bedroom replacement dwelling was completed in December 2017. The combination of traditional stone for the buildings plinth combined with the zinc cladding wrapping over the top and large modern windows creates a fantastic looking dwelling in a great location.

Large open plan rooms combined with double height spaces and feature windows create a great internal environment for the client whether they are entertaining guests or just want to put their feet up and enjoy the views. A feature staircase in the main entrance creates a great focal point. The kitchen, bathroom and en-suites have been designed with a modern look and feature walls and light fittings add interesting features throughout. Another great project to be involved with and one which the client was very happy with the end product.

Beast from the East

Only Ed and Stuart brave the elements to defeat the Beast from the East and make it in to work today. All those less hardy types couldn't cope with the single figure cm of snow. At least Skipton Road is looking the quietest it has in ages.

20180228_105253.jpg

Replacement Dwelling Harrogate

Stuart was on site yesterday to visit the works at our replacement dwelling project on the outskirts of harrogate. The windows are now in and the exterior of the project is looking a lot more complete, with external lighting, downpipes and window flashings complete. Inside the boarding out for the plaster is well under way and the internal spaces are becoming a lot more visible. We cant wait for the next step and finishing items to start going in.

New Dwelling Harrogate

Now we’re out of the ground the stone masons are really cracking on! Masonry is up to first floor level in the traditional wing and window sill level in the modern wing of the building. We can now see the large window and door openings in the traditional wing which will maximise natural light and offer the residents great views of the surrounding countryside. The first elements of the stone detailing, the quoins, have been built in which look great. When walking around we can get a sense of the internal spaces which the client is very happy with. Next step is to get some steel installed and the timber first floor structure.

New Dwelling Harrogate Area

This is the first Blog update for our latest new build house to commence on site. Planning was granted in April and ever since it has been full steam ahead to start building this summer. Site clearance and foundations have progressed well despite the British summer weather trying it’s best to put a dampener on progress with all this rain!

REPLACEMENT DWELLING HARROGATE

It has been a while since any updated on our ongoing projects, however there are a few planning updates to come and several projects are continuing to move forward on site. First of the updates is to our replacement dwelling on the outskirts of Harrogate. The VM zinc cladding by subcontractor Varla cladding is nearing completion and has completely changed the look of the project, we are very happy with the finish and it complements the excellent stonework in the sunlight. The main contactor Ashley Thompson Ltd are currently awaiting delivery of the glazing which will again change the look of the project and allow the second fix internals to commence.

Site Progress - Replacement Dwelling Harrogate

The stone plinth is now complete and looks great. The timber frame at first floor level is also complete and ready to be clad in a standing seam Pigmento Brown Zinc by VMZinc. When walking round the dwelling we now get a feeling of the impressive double height and vaulted spaces with equally impressive views out over the surrounding countryside. M&E first fix is progressing well. Next job is the window installation.